KARTAA Verification Principle: Every progress claim must be supported by geo-tagged photo evidence, matched to a BOQ item, and reviewed by a qualified engineer. KARTAA assists verification — it does not certify automatically.

WMM CompactionVerified
56+200WMM LayerS. Pillai23 Aug 20266 photosBOQ 1.3
WMM SpreadingVerified
54+800WMM LayerS. Pillai22 Aug 20264 photosBOQ 1.3
DBM Layer 1Pending
59+500DBM LayerA. Sharma21 Aug 20263 photosBOQ 1.4
DBM CompactionPending
61+000DBM LayerA. Sharma20 Aug 20265 photosBOQ 1.4
GSB CompactionVerified
48+500Sub-base (GSB)S. Pillai15 Jul 20268 photosBOQ 1.2
DBM Layer 2Flagged
62+400DBM LayerA. Sharma19 Aug 20262 photosBOQ 1.4
Sub-grade PreparationVerified
42+000Sub-gradeR. Kumar20 Mar 202412 photosBOQ 1.1
DBM PavingRejected
63+800DBM LayerA. Sharma18 Aug 20261 photosBOQ 1.4

Progress Intelligence

Evidence Coverage78%

of BOQ items have photo evidence

Verification Rate62.5%

5 of 8 submitted entries verified

GPS Match Rate87.5%

1 chainage mismatch flagged

Pending Actions

2 entries awaiting PM verification
1 GPS mismatch requires field re-check
1 rejected entry needs resubmission
Temperature records missing for DBM entries

Assisted verification,
never automated certification