NH-48 Bypass Package 3

Back Manage TeamActive
Physical Progress
77.1%
vs 87% planned
KARTAA Score
82/100
Evidence + BOQ + Schedule
Schedule (SPI)
0.88
−12% behind schedule
Cost (CPI)
0.94
₹4,79,00,000 spent
Start:12 Mar 2024
Target:30 Nov 2026
PM:Rajesh Kumar
Site Eng.:Suresh Pillai
Length:25.5 km
Budget:₹6,21,40,000
Updated 23 Aug 2026, 18:42 IST

Chainage Progress Timeline

42+00067+500 · 25.5 km

Layer-wise view
42+000Sub-grade
12 photosBOQ 98%100%
48+500Sub-base (GSB)
18 photosBOQ 96%100%
54+000WMM Layer
9 photosBOQ 91%88%
59+500DBM Layer
5 photosBOQ 84%52%
63+000BC Layer
0%
CompletedIn ProgressNot Started