Industrial DPR
Today's DPR Entries
3
Zone A, B, C logged
Photo Evidence
6
3 verified · 2 flagged
Verification Rate
58%
3 of 6 entries verified
Avg Evidence Score
73
KARTAA photo quality
KARTAA Photo Evidence Principle
Every DPR entry must be backed by geo-tagged, timestamped photo evidence. KARTAA scores reflect evidence quality, quantity, and verification status — not just quantity reported.
Daily Progress Entries
6 entries · Last 3 days
| Date | Zone / Activity | Planned | Achieved | Workforce | Evidence | Status | Engineer |
|---|---|---|---|---|---|---|---|
| 23 Aug 2026 | Zone A Structural Steel Erection | 45 MT | 38 MT 84% | 24 | 8photos | Verified | P. Nair |
| 23 Aug 2026 | Zone A Electrical Cable Laying | 320 m | 290 m 91% | 12 | 5photos | Pending | A. Patel |
| 23 Aug 2026 | Zone B Structural Steel Erection | 60 MT | 55 MT 92% | 28 | 11photos | Verified | P. Nair |
| 22 Aug 2026 | Zone C RCC Foundation | 180 m³ | 165 m³ 92% | 35 | 7photos | Flagged | S. Verma |
| 22 Aug 2026 | Zone D RCC Foundation | 120 m³ | 80 m³ 67% | 22 | 3photos | Flagged | M. Rao |
| 21 Aug 2026 | Zone A Mechanical Equipment Installation | 4 units | 3 units 75% | 18 | 9photos | Verified | K. Singh |