NH-19 Pkg 1: No verification activity recorded for DBM layer at 38+500–40+000 in 21 days. KARTAA score at risk of automatic downgrade.
KARTAA score fell from 71 → 48 over 7 days. Evidence gap and GPS mismatch detected. Immediate site inspection required.
WMM layer BOQ consumption at 94.2% with 18% of chainage remaining. Projected overrun: ₹ 12.4 Lakhs. Review quantity takeoff.
DBM layer progress is 8 days behind planned schedule. SPI = 0.88. Current rate insufficient to meet milestone by 15 Sep 2026.
Density test results for WMM layer at 52+000–54+500 not uploaded. Required before proceeding to DBM layer.
No site photos uploaded for NH-19 Pkg 1 WMM layer in 14 days. Evidence continuity score will drop below threshold.
Monthly Progress Report for Jul 2026 has been generated and shared with client portal users.
BOQ match for Sub-base (GSB) at NH-19 Pkg 1 is 79%. Quantity variance of 4.2% detected. Review drawing takeoff.
GPS accuracy for 3 photo submissions at DL Exp. Pkg 2 is below 10m threshold. Re-submission required.