KARTAA OS
Industrial KARTAA Score
74/100
KARTAA Verification Score
Industrial Grade B
Greenfield Steel Plant — Phase 1
Grid
78
Activity
72
DPR
81
Photo
68
Schedule
71
Composite Score (weighted)74/100
0 — Unverified55 — Acceptable70 — Good85 — Excellent100 — Perfect
Verification Dimension Radar
5-dimension score profile for this project
Zone-wise Dimension Breakdown
Active zones only (E & F not started)
Dimension-wise Analysis
Grid Completion
Weight: 20%
78
Zone × Activity matrix completion rate with dependency sequencing compliance
Zone D structural blocked — dependency unresolved
Zone E & F not yet initiated
Activity Quality
Weight: 25%
72
Workmanship quality, material compliance, and inspection sign-off rates
Zone C rebar spacing non-conformance flagged
Zone D soil bearing test pending
DPR Compliance
Weight: 20%
81
Daily progress report submission rate, accuracy, and timeliness
2 DPR entries pending verification
Zone D DPR achievement vs plan gap >30%
Photo Evidence
Weight: 20%
68
Geo-tagged photo evidence quality, coverage, and verification status
Zone C & D evidence flagged for non-conformance
Average photo score below 70 threshold
Schedule Adherence
Weight: 15%
71
SPI-based schedule performance across all active zones and activities
Zone D SPI 0.61 — critical delay
Zone A mechanical at risk (+14 days)
Zone-wise KARTAA Scores
Click a zone row to drill down
| Zone | Grid | Activity | DPR | Photo | Schedule | Composite | Grade | Trend |
|---|---|---|---|---|---|---|---|---|
| Zone A | 88 | 85 | 91 | 86 | 82 | 86 | A | |
| Zone B | 82 | 80 | 88 | 84 | 88 | 84 | A | — |
| Zone C | 65 | 58 | 72 | 52 | 74 | 64 | C | |
| Zone D | 42 | 44 | 55 | 44 | 38 | 45 | F | |
| Zone E | — | — | — | — | — | N/A | — | — |
| Zone F | — | — | — | — | — | N/A | — | — |
KARTAA Industrial Verification Principle
The Industrial KARTAA Score is a composite of 5 weighted dimensions: Grid Completion (20%), Activity Quality (25%), DPR Compliance (20%), Photo Evidence (20%), and Schedule Adherence (15%). A score below 60 triggers mandatory PM review. Scores are never auto-certified — all flagged items require human sign-off.