Railway Progress Report

KARTAA Rail Corridor Demo Project

RailwayDemo / Synthetic

Fictional Central India Rail Corridor · Central Railway · Nagpur Division

120+000206+000Route: 86 kmContract: ₹3,250 CroreReport Date: 25 Aug 2026
48%
Planned Progress
44%
Actual Progress
-4pp
Schedule Variance
Behind Schedule
-4pp
Overall Progress
44%/ 48%
-4pp
Track Laying
38%/ 42%
-7pp
Formation
61%/ 68%
-6pp
Stations
22%/ 28%
-7pp
Bridges & Structures
55%/ 62%
-4pp
OHE / Electrification
18%/ 22%
-3pp
Signalling & Telecom
12%/ 15%
CodeActivityBOQ QtyDone QtyPlan%Actual%VarProgress
1.0Earthwork & Formation42,00,000 25,62,00068%61%-7pp
2.0Drainage Works86,000 m47,30058%55%-3pp
3.0Track Works — Ballast3,20,000 1,15,20040%36%-4pp
3.1Track Works — Sleepers2,58,000 Nos.87,72038%34%-4pp
3.2Track Works — Rail Laying1,72,000 m65,36042%38%-4pp
3.3Turnouts48 Nos.1230%25%-5pp
4.0Bridges & Structures24 Nos.1362%55%-7pp
4.1Culverts68 Nos.4875%70%-5pp
4.2ROB / RUB12 Nos.545%42%-3pp
5.0Stations & Platforms8 Nos.228%22%-6pp
6.0OHE Foundations3,440 Nos.61922%18%-4pp
6.1OHE Structures3,440 Nos.34412%10%-2pp
7.0Signalling & Telecom8 Locations115%12%-3pp
8.0Level Crossings15 Nos.965%60%-5pp
9.0Testing & Commissioning8 Sections00%0%0pp
FormationTrackOHEStation
Segment (km)Formation%Track%OHE%Station%
Ch. 120–130+00080%72%15%45%
Ch. 130–140+00072%48%8%30%
Ch. 140–150+00060%38%20%
Ch. 150–160+00048%28%15%
Ch. 160–170+00040%12%
Ch. 170–180+00028%0%
Ch. 180–190+00015%0%
Ch. 190–206+0005%0%
Track Works
Ballast · Sleepers · Rail · Turnouts
Ballast Spreading36% / 40%
Sleeper Installation34% / 38%
Rail Laying38% / 42%
Turnouts25% / 30%
Bridges & Structures
Bridges · Culverts · ROB/RUB · Level Crossings
Bridges (13/24)55%
Culverts (48/68)70%
ROB/RUB (5/12)42%
Level Crossings (9/15)60%
Stations & Platforms
8 Stations · Platform Works · Buildings
STN-001 — Fictional Nagar45% In Progress
STN-002 — Demo Junction30% In Progress
STN-003 — Synthetic Halt15% In Progress
STN-004 to STN-0085% Foundation
OHE & Signalling
Electrification · Signalling · Telecom
OHE Foundations18% / 22%
OHE Structures10% / 12%
Signalling Locations12% / 15%
Telecom Infrastructure8% / 10%
20
Total Entries (Aug)
15
Approved
4
Pending Review
1
Rejected
MonthTotalApprovedPendingRejectedApproval Rate
Apr 2026282422
86%
May 2026312821
90%
Jun 2026262231
85%
Jul 2026302721
90%
Aug 2026201541
75%
PlannedActual
48%
Current Planned
44%
Current Actual
-4pp
Schedule Variance
29 / 48
Months Elapsed
2
Requires Verification
2
Watch
1
On Track
Formation — Earthwork
150+000 – 170+000
REQUIRES VERIFICATION
Planned
48%
DPR
61%
Observed
55%
Variance
6pp
Action
Field check scheduled
Track Laying — Rail
140+000 – 160+000
WATCH
Planned
42%
DPR
38%
Observed
35%
Variance
3pp
Action
Monitor weekly
Stations — Platform Work
128+000 – 128+600
WATCH
Planned
28%
DPR
22%
Observed
20%
Variance
2pp
Action
Review DPR entries
Bridges — Substructure
135+200 – 135+800
REQUIRES VERIFICATION
Planned
62%
DPR
55%
Observed
48%
Variance
7pp
Action
Structural audit pending
Earthwork — Embankment
120+000 – 130+000
ON TRACK
Planned
85%
DPR
80%
Observed
78%
Variance
2pp
Action
Progress Intelligence compares Planned vs DPR Reported vs Observed. Flags are advisory only — not automatic certification. Field verification required for all exceptions.

KARTAA OS · Railway Progress Report · 25 Aug 2026 · Demo/Synthetic Data Only

This report uses fictional project data for demonstration purposes. No real railway project information is included.