Progress Intelligence Engine
Avg KARTAA Score
Across 3 active projects
Critical Bottlenecks
Require immediate PM action
Verification Rate
Evidence submitted on time
Anomalies Detected
This week across all projects
KARTAA Verification Score — Weekly Trend
All active projects · Jun – Aug 2026
Scoring Logic by Phase
NH-48 Pkg 3 · Evidence + BOQ + Schedule components
Risk Heatmap — Phase × Project
Verification risk level per construction phase across all active projects
| Project | Sub-grade | Sub-base | WMM | DBM | BC |
|---|---|---|---|---|---|
| NH-48 Pkg 3 | 93 Clear | 91 Clear | 84 Medium Medium: Density test pending | 71 High High: GPS mismatch + low evidence | — Medium Medium: Not started |
| NH-19 Pkg 1 | 88 Low | 79 Medium Medium: Partial BOQ match | 65 High High: Evidence gap >14 days | 48 Critical Critical: No verification in 21 days | — Medium Medium: Not started |
| DL Exp. Pkg 2 | 96 Clear | 94 Clear | 88 Low | 81 Medium Medium: Schedule lag 8 days | 72 Low |
Verification Dimension Radar
Cross-project scoring across 6 verification dimensions
PM Action Required
3 bottlenecksVerification stalled 21 days
Assign site engineer immediately
Evidence coverage <20%
Upload minimum 6 photos per 1,000 m²
BOQ variance +18%
Cross-check drawing takeoff vs. site measurement
Performance Anomalies
Auto-detected deviations across all active projects
DBM verification stalled — no entries for 21 consecutive days
Detected: 23 Aug 2026
WMM layer evidence gap: only 2 photos for 3,400 m² area
Detected: 22 Aug 2026
DBM BOQ quantity reported 18% above drawing takeoff
Detected: 21 Aug 2026
KARTAA Score dropped 4 points in 7 days — GPS mismatch flagged
Detected: 20 Aug 2026
DBM paving 8 days behind revised baseline schedule
Detected: 19 Aug 2026
Overall KARTAA Score declined from 78 → 71 over 3 weeks
Detected: 18 Aug 2026
Intelligence scores are computed from evidence submissions, BOQ cross-references, GPS accuracy, and schedule adherence. All findings require PM review before any formal certification. KARTAA OS v1.0 — Phase 2