KARTAA OS

Railway Dashboard

KARTAA Rail Corridor Demo Project

RailwayActive

Fictional Central India Rail Corridor · Central Railway · Nagpur Division

120+000206+000Route: 86 kmBroad Gauge (1676mm)Double Line
₹3,250 Crore
Contract Value
8
Stations
24
Bridges
12
ROB/RUB
68
Culverts
15
Level Crossings
-4pp
Overall Progress
44%/ 48% planned
-4pp
Track Laying
38%/ 42% planned
-7pp
Formation
61%/ 68% planned
-6pp
Stations
22%/ 28% planned
-7pp
Bridges & Structures
55%/ 62% planned
-4pp
Electrification / OHE
18%/ 22% planned
-3pp
Signalling & Telecom
12%/ 15% planned

Overall Progress Trend

Planned vs Actual · Apr 2023 – Aug 2026 · Demo/Synthetic Data

PlannedActual

Recent DPR Entries

Last 5 entries · Demo/Synthetic Data

View All
Rail LayingApproved
Ch. 134+200 – 134+850850 mR. Sharma
25 Aug 2026
Platform Work — STN-001Pending
Ch. 128+400 – 128+60075 m²A. Verma
25 Aug 2026
Ballast SpreadingApproved
Ch. 131+000 – 131+500420 m³R. Sharma
24 Aug 2026
Earthwork — EmbankmentApproved
Ch. 120+000 – 121+2001,250 m³P. Nair
24 Aug 2026
Sleeper InstallationSubmitted
Ch. 134+000 – 134+200350 Nos.R. Sharma
23 Aug 2026